The first unit of the ultra-high pressure gas injection compressor, manufactured by China Oil Blue Ocean Petroleum Technology Inc., with an export pressure of 52MPa and a daily displacement capacity of more than 230,000 square meters, was officially put into operation at the site of 4-6 gas injection station in Shunbei District 2 recently.
The self-developed solar wellhead control system was successfully launched.
Sinopec Northwest Oilfield Dazhongba Gas Storage Project Dazhongba Gas Storage Project 52mpa high pressure gas injection compressor was successfully put into operation!
It integrates original technologies such as grid tube oil-water-solid separation and high-efficiency lateral diffusion oil-water-solid separation, and has the functions of gas-liquid separation, water separation and produced water treatment, and can directly separate qualified oil-water from the produced fluid of oil wells.